Canadian telecom group Telus will no longer take part in two projects to build artificial intelligence data centres in Vancouver. CBC News says the company confirmed this week that it is stepping away, and the technology outlet BetaKit reports the same development.
What Telus announced
A company spokesperson said Telus had decided not to go ahead with co-developing the two sites, announced in May, with the property developer Westbank, according to CBC. Telus says it wants to focus on expanding an existing data centre in Kamloops. The first site, a building in the Mount Pleasant neighbourhood that was formerly Hootsuite's headquarters, was meant to open by the close of the year. The second, downtown on West Georgia Street near BC Place stadium, was planned for 2029. CBC notes that Telus gave no reason for pulling out.
Westbank keeps the projects going
Westbank tells CBC and BetaKit that both projects are continuing as planned, with a new partnership due to be unveiled over the next few months. According to BetaKit, the first site covers about 100,000 square feet and the second about 400,000. Both sites are still waiting for municipal decisions, including on zoning.
Explanations offered, none confirmed
With no statement from Telus, several readings are circulating. BetaKit relays an anonymous source whom the Globe and Mail quotes; that person points to a lack of local support. Hundreds of people marched in Vancouver this year against these centres. Guerric Haché of the group No AI Vancouver tells CBC that he believes public reaction weighs on the decisions of companies like Telus; he also mentions growing worries about the stability of the AI market. These remain interpretations: the company has confirmed nothing.
A heavy financial backdrop
BetaKit points out that Telus carries growing debt and is trying to reorganise its non-telecom businesses; its share price has fallen about 25% since January. CBC adds that Quebecor has tabled a takeover offer worth 31 billion dollars, which Telus says it is examining.
Why it matters
Telus pulled out of these two projects without giving a reason. For now the withdrawal says nothing about the future of the two sites, which Westbank intends to see through with another partner.